MOULD PRODUCING FLOW CHART

1. Work out 3D mould project
according to the customer request
and union mould standard. |
|

|

2. Send the 3D mould project
to customer via. ftp.
or email for customer
confirmation or modification for the mould. |
|

|


3. After all 3D mould project confirmed, union mould will work out the
detailed 2D drawing and begin the steel cutting.At the
same time, our QC Dept. starts to follow the project and send to the customer the tooling & processing schedule
|
|

|

4.
Mould base and components ordering and preparation
|
|

|

5. Production Dept. begins
insert block precision tooling and
the QC Dept. follow the project closely and update the tooling & processing schedule weekly,
report to the customer by photos |
|

|

|
6. Check
all systems of the moulds before assemble them.
|
|

|

7. Adjust
and assembling the mould.First stage necessary polishing |
|

|

8. Mould
1st Testing (or 2nd Testing if necessary), check the
product dimension and take down the mould testing report
|
|

|
|
|